Hi, starting a new job this week. One of the 1st things they have mentioned is extracting data from SIMS and putting it into Facility CMIS - yikes!

 

Has anyone been through this - or did you get someone in to do it?

 

Thanks

Posted
the migration from sims to cmis is normally done as part of the commissioning processes and I must say is the worst part of using the facility system. best to run the two side by side for a while to make sure everything is up and running properly. Migrating timetables is the worst part so its best to use sims for your current year and start setting up cmis for the coming year, including writing the timetable using scheduler.
Posted
best to run the two side by side for a while to make sure everything is up and running properly.

 

To add to this, I suggest making the old sims database non-writable. The last thing you want is some muppet continuing to add data to the old system.

Posted

Indeed - CMIS do the migration under the package described above.

 

I would seriously contemplate leaving SIMS though - I'm currently supporting a network that made the move, lease to say there not all that impressed. I understand what situation you're in though - you've probably not got much say in the matter now!

 

Good Luck!

Posted
Indeed - CMIS do the migration under the package described above.

 

I would seriously contemplate leaving SIMS though - I'm currently supporting a network that made the move, lease to say there not all that impressed. I understand what situation you're in though - you've probably not got much say in the matter now!

 

Good Luck!

 

Do you mean have it in parallel running or actually just use Sims.net?

Posted

We moved to CMIS and then moved back again - in fact I've just converted had the converted database back of Capita today!

 

There is a import facility in CMIS from SIMS and also SIMS.Net - I haven't tried these as Serco Derby did the conversion for us.

Posted

One of my schools made the move from SIMS to Facility coming up to 4 years ago now. At the time we were having serious issues with SIMS. I would say personally say that Facility is better (although I can't compare it to the current SIMS). You do have to have a couple of really good people on board that will really lead the move and continue to lead throughout the first year or two of the move. You will hit hurdles and we found that the data migration from SIMS was far less complete than we had expected.

I would recommend that you speak to a couple of schools, locally if possible that will help you implement a real world database a help advise you on some important decisions that need to be made. More than willing to help if you need it.

Facility is very flexible and customisable. Reporting in facility is very different to SIMS. Much better in some ways but sometimes I feel you need to be a rocket scientist to understand them. They are completely rewriting their reporting system just now which should help.

Let me know if you need a hand with anything and I'll do my best.

Good luck!

Posted
Do you mean have it in parallel running or actually just use Sims.net?

 

If you've got to make the move leave them running parallel definitely! Otherwise don't give CMIS your money! hehe

Posted

We transferred from SIMS to Facility a year and a half ago. I would emphasise the following, some of which are mentioned above. Serco will transfer your data across, however for us they only transferred the 1 years worth of data. This meant that we still have to go into SIMS to look for historical information. They did not transfer any of our assessment or behaviour log information. I was not part of the decision making process and only started overseeing after the switch over.

 

We ran with Facility only from the start and did not run 2 systems in tandem. There are benefits to both, we were forced to fully embrace Facility immediately. However the data transfer was not perfect and there is a lot of checking to do. We ran with Facility from September 1st and I ran the Census in late September with it. I would advise using the 2 systems in tandem for no more than 1 term.

  • 4 weeks later...
Posted

Thanks for all the advice folks. In my 3rd week - no regrets!

 

You were right about Serco, they are "converting" data for us. Had more trouble getting exclusive access to the sims database files than anything else!

 

The current school is actually closing down and an Academy will be opening up on the same site - they wanted the new MIS - something to do with being better at handling vertical tutor groups.

 

I don't think that the Academy will need historical data. All that is being sent to the LA.

  • 2 weeks later...
Posted
Thanks for all the advice folks. In my 3rd week - no regrets!

 

You were right about Serco, they are "converting" data for us. Had more trouble getting exclusive access to the sims database files than anything else!

 

The current school is actually closing down and an Academy will be opening up on the same site - they wanted the new MIS - something to do with being better at handling vertical tutor groups.

 

I don't think that the Academy will need historical data. All that is being sent to the LA.

 

Be aware that if moving from september the academy will need at least the last years historical data in the system in order to do Plasc which accesses the previous datasets attendance figures.

  • 2 weeks later...
Posted

I just want to say thanks for all the offers of support. No doubt I will be asking more questions soon!

 

The data has been converted and is now in CMIS, but I haven't checked it out yet.

 

The structure of the Document Storage bit is something I'm interested so I'd be grateful for any pointers with that.

 

Tazz

Posted

 

The structure of the Document Storage bit is something I'm interested so I'd be grateful for any pointers with that.

 

Tazz

 

There is a document available to download from the support website explaining how to set it up.

 

The process involves copying the documents to a location on the server specified at the set up stage easy, then attaching each document to the relevant student (tedious!).

Posted
There is a document available to download from the support website explaining how to set it up.

 

The process involves copying the documents to a location on the server specified at the set up stage easy, then attaching each document to the relevant student (tedious!).

 

This is actually incorrect. Files (including videos etc) can be attached from any location to a student record, the copy is automatically made in the specified location. Any reports generated from Facility are automatically converted to PDF format and attached to the student record, for example end of year reports can be run for an entire year group and are automatically attached to the students record and visible via the web in ePortal.

 

It is also possible to restrict access to documents to teachers, parents or pupils or any combination of these.

  • 3 years later...
Posted
I am facing a similar issue at the moment..m supposed to join my new job as DATA/EXAMS manager in a school in london that uses CMIS but i have always worked on SIMS so just a little nervous and sceptical. Does anyone have an exams and/or asessment manual that i can get hold of?

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now



×
×
  • Create New...