jimbopembo Posted June 24, 2022 Posted June 24, 2022 I'm struggling to get quotations due to a shortage of available components. It would be interesting to hear from anyone else with this problem......
Andycat Posted June 24, 2022 Posted June 24, 2022 We ordered new infrastructure in February, and we still haven't got it in due to a delay in connectors. The rest of the hardware is here, but only arrived at the end of May. HP stuff! 1
dmj Posted June 24, 2022 Posted June 24, 2022 Have you thought about using someone else's computers? I just decommissioned 6 servers, ordered new ones; they all arrived, were configured and added to the cluster in under 2 min! module.gke.google_container_node_pool.pools["jenkins"]: Creation complete after 1m34s Apply complete! Resources: 6 added, 0 changed, 6 destroyed. Seriously though, cloud really does take a lot of the hassle away from infrastructure.
Shadow_Walker Posted June 24, 2022 Posted June 24, 2022 Not had any issue with getting servers, ordered some HP ones a couple of weeks back and arrived this week.
mikkydoos Posted June 24, 2022 Posted June 24, 2022 Nor me... in fact got one sitting on my floor that came yesterday. Ordered it on Tuesday at 4.00pm. If a supplier can't supply, don't use them. Go talk to one of the giants. They have clout with the manufacturers. 1
jimbopembo Posted June 24, 2022 Author Posted June 24, 2022 Nor me... in fact got one sitting on my floor that came yesterday. Ordered it on Tuesday at 4.00pm. If a supplier can't supply, don't use them. Go talk to one of the giants. They have clout with the manufacturers. Who did you order from?
mikkydoos Posted June 24, 2022 Posted June 24, 2022 Ebuyer Business. DELLs. (Theres a similar thread going on re getting hold of switches. Said the same.) EB are good.
jimbopembo Posted June 24, 2022 Author Posted June 24, 2022 Thank you. I’ve ended up communicating directly with Dell. For the spec I’m looking for there’s a shortage Nics at the moment but they’re doing the legwork. Looking like a 2 to 3 month wait.
jmak Posted June 24, 2022 Posted June 24, 2022 (edited) Haven't been buying servers, but have been buying other stuff from Dell. I've been choosing from what's available for very quick delivery and where necessary adding components myself to match the specs I need. They seem short on memory and large SSDs at the minute... Edit: we also had a warranty claim on a monitor which was supposed to be advance replace (ie send out replacement before receiving faulty one). When I hadn't heard anything for a week I chased the account manager and they said it was a 2 month wait for an identical model, but we could have a silver one next day... Just reinforcing the point about checking what's in stock. Some stuff has been arriving next day, some almost identical kit is on back order. Edited June 24, 2022 by jmak
XiJ Posted June 24, 2022 Posted June 24, 2022 I’m after HP servers and sff hard drivers. No chance. Current estimates of of august. I’m doubtful it’ll be that soon
jmak Posted June 24, 2022 Posted June 24, 2022 I don't trust anything over 6 weeks. If it ain't on a boat from China, it probably doesn't exist yet.
XiJ Posted June 24, 2022 Posted June 24, 2022 HP Laptop and desktop however seem to relatively plentiful. Just need some on-prem servers for a short while.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now