We are thinking about moving away from SWGFL and have just had the termination fees come through to us. They want around £1000 per site to move away from them. The costs are broken down as the following:

 

Unrecovered Costs

core £300

software £100

 

Breakage costs

Telecoms £0

Admin £150

Engineering £350

Lost Profits £100

 

To me this seems pricey but SWGFL was put in before my time and I have no idea what was signed contract wise and if we really have to pay this to leave? Does anyone have experience with this?

 

Cheers

Posted

This is good to know... we are slowly severing our links with them, hosting our domain internally and moving our registrar and name servers to another provider to manage our own subdomains.

 

Please, let me know how this goes as i'm going to have to do it before august.

Posted
Thanks Achandler, we are an academy now so I doubt the local council will get involved but 1k does seem excessive. I am not too sure what to do, pay it, argue it, or do something else?
Posted

I would check the contract to be honest, if your contract has expired then you shouldn't have costs.

 

If it has expired then I can see why they want to charge you. When we left out LA for the internet connection, software they provided etc, we were at the end of our contract and just gave them written notice we were leaving, they arranged to collect some of their on site equipment and then that was it.

Posted
Thanks Achandler, we are an academy now so I doubt the local council will get involved but 1k does seem excessive. I am not too sure what to do, pay it, argue it, or do something else?

 

Can you get hold of the contract?

 

I would try that and see what it says.

Posted

Do it at the end of the contract, so that you incur no costs at all. Have some suppliers on the ready and negotiate deals ready for when the contract expires. I have found most tend to end in April with councils as they like to do it all for the financial year.

 

Some of the fee's seem a bit ridiculous, admin - this is quite steep but an admin fee is expected, engineering - ok, so they have to cover the cost of recovering the equipment, removing the line etc but the one that gets me is "Lost Profits"...sorry, that is crazy!

Posted

We will be out of contract as far as I know we have waited a year to be out of contract. The contract ends in April and we are giving 6 months notice. I have found a copy of the SWGFL user agreement online and it states:

 

termination or expiry of this Agreement the Service User shall:

 

11.6.1 pay to SWGfL any Termination Fees due under or in relation to this Agreement;

 

11.6.2 pay to SWGfL all arrears of any Charges due to SWGfL under this Agreement up to the

date of termination; and

 

11.6.3 return to SWGfL any of the Confidential Information and provide a written certification that

such Confidential Information has not been retained save to the extent this is required in

relation to the Services.

 

So I don't know what we can do. I agree some of the costs seem excessive, should I ask for a detailed breakdown of the costs?

Posted

Well I would say the same but it states "for the avoidance of doubt, in cases where terminations have been requested in which costs apply, the process will not commence until a purchase order has been recieved to cover the costs".

 

I think we will have to ask for a breakdown but I am still unsure if you are out of contract if they can even charge fee's but I am not sure either way.

Posted

If you are out of contract, there should be no charges -

I have moved a few schools away in Derbyshire and Derby City, from LEA control. The only charges that I have come across are for transferring mail accounts and "decommissioning" services. Just make sure you have a backup system in place first though. I buy a temporary domain, .org or something for £10.80 from One.com. Register that with Office 365 for Education or Google Apps and use that to set up the new system, when you get control of the domain , just switch over the default domain name to the .sch one.

Look for bits in the contract concerning auto-renewal, but If you kick up enough fuss, there should be no charge.

Posted
Termination fees, mad and frustrating as it sounds, are not uncommon whether at end of contract or not. If the termination fee is written into the contract there is no get out clause, although £1000 is pretty steep.
Posted

Stop paying them at the end of the contract, what're they gonna do, stop your service?

 

I doubt the fees would stand up in court, and the cost of taking you there would outweigh the loss anyway.

Posted
It worries me greatly that someone at SWGfL isn't working hard at keeping customers. Apart from the odd glitch I have found them pretty good at providing the services and support schools need - seems a bit crazy that an organisation will actively assist its clients to migrate e-mail services to Microsoft. I believe SWGfL is part of RM if I w a shareholder in TM I'd be seriously concerned that the management at SWGfL isn't fighting to keep and build the services it provides.
Posted

This seems very odd to me. Can you drop me a PM, I have some contacts in swgfl.

 

As the contracts have to be renewed each year, it figures some won't and then service is terminated. You have given notice of non renewal, so I don't see the problem

Posted

Please remember that termination is not simply unplugging a cable. Some RBCs / LAs will have factored this cost in during the period of the contract and so no cost is apparent to schools directly, but the cost is still there. The costs as described are perfectly reasonable and comparable to other similar terminations.

 

Refusal to pay will probably mean that the funds have to be sourced from somewhere else in the LA, meaning it cuts into money available for other services. Even if you are an academy, you are taking money away from services used by your families.

Posted

If what GrumbleDook is saying is true then it would appear that some LAs just assume you would never want to leave so they don't tell you that you are going to be charged to leave (I would be money on this never being told to a school when they signed up).

 

It is the same above attitude that no one will leave that has lead LAs to become uncompetitive with leaving, prices quoted from our local LA were nearly double the cost of going independent. When we told them our costs of leaving their prices were suddenly able to go lower (virtually matching going independent), which makes you wonder why it was £10k+ extra annually to start with.

Posted
We left the swgfl last year after giving 3 months notice ..... We paid no termination fees attall .... As far as I can tell termination only comes into play if the contract is current ... if its gone past its final date and its not renewed after having given the contracted notice then its not a contract anymore ..

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now



×
×
  • Create New...