For us there's quite a chunk to get done:

 

12 new iPads to set up

85 new staff laptops

12 new student laptops

Recondition some old laptops for use by students (about a dozen)

40 new desktop PCs

Remove 9 old switches and get rid of an old network in the primary school, moving their PCs to the whole site network instead

Virtualise 7 servers onto 2 physical, by moving all data onto a NAS, formatting the DAS array and rebuilding for reliability and speed, then put it all back, with virtual servers hosted on it too. All interconnected by a new 8Gbit FC switch.

Upgrade 20 iMacs to latest OS X, also install Windows image to them as well for bootcamp.

Set up Apple server, integrate all Apple computers with Windows network

Install 4 new iMacs

Install RAM upgrades in 335 PCs and laptops

Upgrade AD to Windows 2008 R2

Migrate all PCs and laptops to Windows 7 and Office 2010

Move some access points from over-dense areas to cover black spots

Set up 30 Google Chromebooks (not confirmed yet, but assumed).

Set up a new digital display box

Set up 2 55" touchscreen LCDs, one mobile, one in a classroom.

Roll out Forefront AV to replace NOD32.

 

2 of us on the job. Its gonna be tight.

 

Taking a long vacation, this should be on everyone list as number 1.

 

Hahaha! Yeah. I'm gonna get a week. That's it.

Edited by localzuk
Posted

Backpacking from Denmark to Moscow, music festivals, xbmc developers conference ;)

 

Oh work? Well might set-up some more redundancy for our servers and get the new ipads setup, and create the parent accounts for TASC insight but that's about it.

 

Nice to see people moving away from CC3 to the freedom of vanilla networks. I doubt you will regret it.

Posted

Busy summer here for me!!

 

- New domain with all new servers & SAN, new usernames for everyone!

- New Exchange 2010 available externally, ditching lea email and hosting our new domain name!

- 18 Apple iMacs in Music

- Currently 11 Casio LED projectors being installed, could be going up to 13/14

- Swapping Library and large open access 64 seat ICT suite over and dividing old library into 2 ict rooms

- 60 new pc's

- upgrades to 30 pc's

- move 50 pc's around the school

- upgrade xenapp, xen desktop, xen server to latest versions and set up citrix gateway for reciever for ipad access

- move from SIMS to progresso

- update website

 

oh 2 weeks holiday at the start of august as well!!

 

The servers were supposed to happen at easter so i booked holiday in summer but plans changed!! (long story!!)

 

Oh and its just me and the work experience lad (being paid) plus the contractors for the specialized bits!

 

Plus whatever else they decide to throw at me as well!!

Posted

Well - strangely enough, I've just had an e-mail from a company called BIST which is asking to quote for prices of various IT equipment based on a copy & pasted list of what I put on my previous post on this thread! :mad:

 

Admins !!!

 

Grrr

 

Pete

Posted (edited)

- Upgrade final 2003R2 server to 2008R2

- Pull more cat5e through to other end of school

- Deployment of iPads

- Deployment of first couple of Macs

- Deployment of Mac Mini server

- Clean up GPOs, staff shares etc

- General software updates school wide

- Get final couple of staff onto domain

- Replace some borked VGA cables to projectors in ceiling

- Get final few staff onto Win7 :)

 

Then off to sunny Portugal! :p

Edited by Blue_Cookeh
Posted

Move to native Windows 2008 r2 domain

Change email domain name

Project manage school moving to a brand new website

Install brand new 10kva UPS on the mains circult

Roll out school wide wireless

Implement Lightspeed Content Filtering System

Retrofit 70 teachers stations with SSD and Win7

Reimage 100 Class PCs with Win7

Help move and relocate PCs (we wont know till the summer break!)

Implement Hyper-v setup(Print server,legacy servers etc)

Redo GPOs

 

5 years of not spending a penny, then all at once lol!

Posted
6 weeks of rebuilding the school website from scratch,

 

nothing else.

 

Well i thought it was just this......

 

Now ive got to do these in three days...

 

Move all IT equipment out of classrooms so they can be redecorated and cleaned then move back after

Clean out server (dust) and remove all unwanted software/files installed

Reimage 30 laptops to be split into three classes

image 30 new laptops for staff

reimage old staff laptops to be distributed around school

all old IT junk to be collected up and stored to be collected

 

The days are not in a row either!

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now



×
×
  • Create New...