hey,

 

i kinda need help, i am a college student studying IT practitioner and i have a question which i am stuggling on, i need to know a little bit about BACKOUT, i have been given a defination about it but it makes no sence at all!!! please help me

 

Thanks Jason

Posted
i need to know a little bit about BACKOUT, i have been given a defination about it but it makes no sence at all!!!

 

What context are you talking about - what is the definition you have been given?

 

--

David Hicks

Posted

Assuming you mean with regard to change control:

 

If a change takes 3 hrs to do, an hour to test and 3 hrs to restore to the original state, you need a minimum of a 7 hr window. At 4hrs, if it's still not working, you restore it as it was so it's working for when people need it rather than keeping hammering away at it.

 

Use of tools like vmware converter to test major changes beforehand saves a lot of grief and wasted time.

Posted

the definition i have been given is:

 

platform and/or application software on all online, machine/servers in a cluster is updated without manually taking each machine/server offline. initially, platform and/or application software for updating is stored in respective directories in an APPLY phase. next,the new platform and/or application software is activated with or withouta trial/test phase in an ACTIVATE phase. where the new platform and/or application software is activated with a trial/test phase, a ROLLBACK phase is either autmatically or manually invoked by the application in the event of a failure of the new software for backing out the new platform and/or application software and reactivateing the previous platform and/or application software . an OFICLAL phase then trasitions the new platform and/or application software to the official state followed by a REACTIVEATE phase for reactivating the backup copy of the previous/old platform and/or application software after the new software has been made official.

 

as you can see this is rather confusing

Posted (edited)
A simple definition would be that if you're making changes and they go pear shaped, the backout plan would be how you abandon the changes and go back to the original configuration. Edited by SteveBentley
said backup when I meant backout
  • Thanks 1

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now



×
×
  • Create New...