Ooo a classic one this. Timetable sent over but not applied correctly. Check out Tools > Academic Managerment > Apply Timetable. Be careful with dates and weeks as you appear to have a 2 week timetable :)
  • Thanks 2
Posted
Thanks. We had a 2 week timetable last academic year. Not this tho?? We've moved from Go4Schools mid year. Just kept the basic reporting and tracking in Go, and dropped lesson registering and behaviour.
Posted
Thanks. We had a 2 week timetable last academic year. Not this tho?? We've moved from Go4Schools mid year. Just kept the basic reporting and tracking in Go, and dropped lesson registering and behaviour.

 

Naming convention led me to believe 2 week timetable, so purely a guess . .

Posted

Yes I was worried by that.

 

Starting that routine I'm getting the 2 week rubbish from last year. Is it ok to go through all of them and reset them to mon, tue, wed etc??

 

LMtransfer.JPG

Posted
So firstly you need to check that the correct version of the timetable has been sent over, as that build is from Sept '17 and is the 2 week version. I would assume not. Care should be taken here and if you have a support contract with someone I would ask them to investigate. If the timetabler is confident sending over the timetable then I would select a start day of today and apply the timetable from today on wards.
  • Thanks 1
Posted

I had a word with myself (I'm the timetabler :p) and pushed the button. All looks good and everything seems to be functional.

 

Just need to get the staff to use it now :D

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now



×
×
  • Create New...