Hi

 

I am currently in the process of overhauling my IT development plan and realigning it with our school development plan and budgets.

 

Some hardware i am having a problem predicting life cycles for (as i have never had to replace them yet). The virtualisation kit is something i am looking to introduce over the next 18-24 months as a phased upgrade.

 

How often would you replace the following, (I know it depends on growth etc but a ball park figure based on experience would be really useful):

  • Core Switch (Currently 3Com 4800G)
  • Edge Switches - Currently HP v1910-48G
  • SAN - 10TB (Currently use about 4TB for document shares and user work areas)
  • Hosts for virtualised system

 

Also going to ask all staff to fill in a survey to ensure that there are no obvious areas i have overlooked and to see where they think development etc is needed. Could just get a lot of criticism but it at least gives a platform for it and shows i am attempting to tackle issues that are bought up by large numbers of staff.

 

Thanks

Posted
How often would you replace the following

In my current school it would be...

 

  • Core Switch - 10 years
  • Edge Switches - 10 years
  • SAN - 4-5 years
  • Hosts for virtualised system - 4-5 years

  • Thanks 1
Posted

You don't really need to plan for the replacement of switches. Personally using entirely HP switches and they're all lifetime warranties, so if they fail I'm covered (though I keep the odd spare, for faster response to failures) Any plans for switching replacements should be on a case by case basis as you find you need more performance or switching capacity. Not something you can really plan for until the situation arises.

 

SAN - 5 to 7 years depending on how reliable the device has been and whether it's meeting performance requirements at the 5th year.

Servers - I'd say the same as above to be honest.

 

Be interesting to see if anyone agrees with me, but that's how i've always seen it.

  • Thanks 1
Posted
Replacement programs should be based on both warranty and on projected improvements. I still chat to folk who had top of the range networks 10 years ago but are now struggling because there is no investment to improve the capacity or technology.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now



×
×
  • Create New...