garethEds Posted May 11, 2018 Posted May 11, 2018 Afternoon All, My journey to improve our HyperV setup continues after being setup a long time ago by @rich_tech. I'm in the process of adding a third node but before I do, I was wondering what the ideal way of cabling this all together is? Two of the servers (HyperV1 and V2) have 6 network ports. The new server has 8 network ports. The SAN is a P2000 G3 and the switch is a Cisco 200 Two notes is working well, but as I learn what I am doing I'm looking for improvements. So any wiring diagrams, advice etc would be gratefully taken on board. Thanks Gareth
Steve21 Posted May 11, 2018 Posted May 11, 2018 (edited) I mean it depends how you have the servers setup really. But the "standard-ish" way of doing it is split each "role" across 2 cards and 2 switches and 2 SAN modules. e.g. Management Team Goes to Card 1 Port 1, and Card 2 Port 1. Card 1 Port 1 goes to Switch 1 Port 1, Card 2 Port 1 goes to Switch 2 Port 1 Then SAN Module 1 Port 1 goes to Switch 1, and SAN Module 2 Port 1 to Switch 2 etc etc Gives you as many failover points as possible should any one card/module/switch die Steve Edited May 11, 2018 by Steve21
garethEds Posted May 11, 2018 Author Posted May 11, 2018 I mean it depends how you have the servers setup really. But the "standard-ish" way of doing it is split each "role" across 2 cards and 2 switches and 2 SAN modules. e.g. Management Team Goes to Card 1 Port 1, and Card 2 Port 1. Card 1 Port 1 goes to Switch 1 Port 1, Card 2 Port 1 goes to Switch 2 Port 1 Then SAN Module 1 Port 1 goes to Switch 1, and SAN Module 2 Port 1 to Switch 2 etc etc Gives you as many failover points as possible should any one card/module/switch die Steve Thanks Steve, Would this sort of information be on the web somewhere? With diagrams etc? Gareth
Steve21 Posted May 11, 2018 Posted May 11, 2018 At a basic level it's like this: So basically no matter what fails it has another connection. Repeat for each Team/Server etc Steve
garethEds Posted May 11, 2018 Author Posted May 11, 2018 At a basic level it's like this: [ATTACH=CONFIG]48915[/ATTACH] So basically no matter what fails it has another connection. Repeat for each Team/Server etc Steve Oooo - thanks Steve. Never thought of using two switches before. I only have one. I assume both switches would then link back to my main central backbone switch. We have both our servers linked together too for failover. I think I may need to re-do ours. Is this how yours is set up? Gareth
Steve21 Posted May 11, 2018 Posted May 11, 2018 Yep else the whole redundancy aspect is reliant on a single switch to fail if you have just a single switch there's not much you can do to stop a major failure if it breaks. Well that's the storage side, generally "best practice" SAN->Host connections should have their own switches. But yes it's the same principle, for example the HOST->Network side, is just two connections into our core switches (Which are stacked), So we have 2 connections in per host for Management, and 2 for VM traffic etc. (Those obviously don't need to go into the SAN switch if you have separate ones). So effectively even if 1 SAN module, 1 Storage Switch, 1 HOST Nic and 1 Core fails you'd still have connection (Hopefully never would happen but yeah!) Steve
garethEds Posted May 11, 2018 Author Posted May 11, 2018 Thank @Steve21 - I'm going to draw this up similar to your diagram. What about IP addressing - I'll get to that next week. Gareth
Steve21 Posted May 11, 2018 Posted May 11, 2018 Excuse my hastly painted example and obviously it's not just one link, but one per item e.g. Management, Traffic, Replication etc etc but: If that makes sense, and then per host you split it per card too Steve
Steve21 Posted May 11, 2018 Posted May 11, 2018 Thank @Steve21 - I'm going to draw this up similar to your diagram. What about IP addressing - I'll get to that next week. Gareth That site depends if you're using multiple switches I guess. We have our iscsi/storage on the 192s and our main networking/traffic on the 10s as those switches don't connection. But basically shouldn't really matter much as long as you keep it standard to make life easier when trouble shooting Steve
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now