Geoff Posted November 22, 2012 Posted November 22, 2012 We're planning to move office, there's one rather large snag however. The previous occupant in a fit of malice decided to cut all of the electrical, telephony and data cabling before they left. The power and telephony have obviously been fixed at the landlord/service providers expense however fixing the internal network cabling has fallen to us. On cursory inspection the situation doesn't look too bad, The cables all come into one room and have been cut where they come under the floor into the room (presumably where the comms cabinet was). There's no extra play in the cabling so I can't simply pull more length in. What is the most cost effective way to fix this? Our current comms contractor wants to recable the entire building at considerable cost.
Dos_Box Posted November 22, 2012 Posted November 22, 2012 Whilst I have no doubt that there is a way to patch (no pun intended) snipped cables inline, I would suggest that it probably wouldn't do the signal quality any favours. It may be best for a complete re-wiring tbh.
AngryTechnician Posted November 22, 2012 Posted November 22, 2012 (edited) Wire up 2 sets patch panels under the floor, one set to terminate the old cabling, and another set to terminate your new extensions. Then connect the two together with patch cables. It won't be pretty, but it should work and it will be relatively cheap. If you have (or can rent) a high-end cable tester it will be able to verify if the cabling is still up to standard with the extra patches. Edited November 22, 2012 by AngryTechnician
plexer Posted November 22, 2012 Posted November 22, 2012 I hate joining cables but our contractor will do it where required and as long as it's tested and passed it'll be ok. Ben
tech_guy Posted November 22, 2012 Posted November 22, 2012 It's a shame they didn't fry themselves when they cut the electrics then....
glennda Posted November 22, 2012 Posted November 22, 2012 We're planning to move office, there's one rather large snag however. The previous occupant in a fit of malice decided to cut all of the electrical, telephony and data cabling before they left. The power and telephony have obviously been fixed at the landlord/service providers expense however fixing the internal network cabling has fallen to us. On cursory inspection the situation doesn't look too bad, The cables all come into one room and have been cut where they come under the floor into the room (presumably where the comms cabinet was). There's no extra play in the cabling so I can't simply pull more length in. What is the most cost effective way to fix this? Our current comms contractor wants to recable the entire building at considerable cost. Could the Comms cabinet be moved to where the cable is able to be pulled back to? Might end up sitting outside the comms room though.
Geoff Posted November 22, 2012 Author Posted November 22, 2012 Could the Comms cabinet be moved to where the cable is able to be pulled back to? Might end up sitting outside the comms room though. That location is not ideal for a 42U rack as it is a corridor.
Guest Guest Posted November 22, 2012 Posted November 22, 2012 As said patch panels. Or if you want to be even tighter cat6 coupler - Google Search
glennda Posted November 22, 2012 Posted November 22, 2012 That location is not ideal for a 42U rack as it is a corridor. Thats a shame!
sonofsanta Posted November 22, 2012 Posted November 22, 2012 The couplers work alright, just terminate the cut cables in a normal 8P8C connector and carry on from there. Not ideal, maybe, but they've worked alright here in the couple of places we've needed to move a socket 10m in the old part of the building.
Andrew_C Posted November 22, 2012 Posted November 22, 2012 I'd go for these. Shouldn't degrade the signal at all, certainly less than two patch panels and leads. In-line join
AngryTechnician Posted November 22, 2012 Posted November 22, 2012 I've used those couplers too in the past, only reason I didn't recommend them first is I suspect there are a lot of cables and the patch might be more manageable.
AngryTechnician Posted November 22, 2012 Posted November 22, 2012 I can see why you'd like to avoid a full recable!
Ric_ Posted November 22, 2012 Posted November 22, 2012 I would suggest coming to a deal with the landlord. If you use couplers, you will need 154 which is expensive and dodgy as hell. If you re-cable, it is expensive but you get nice new, certified, points. I would suspect that you should give serious consideration to finding other premises as an option... and let the landlord know that fact.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now