MIS Systems Thread, Changing the Timetable Cycle in Nova t6 in Technical; I am in a large school with KS 3,4&5. The Cycle and Model and timetables have all been completed for ...
  1. #1
    jdk
    jdk is offline

    Join Date
    Jul 2012
    Location
    manchester
    Posts
    1
    Thank Post
    0
    Thanked 0 Times in 0 Posts
    Rep Power
    0

    Changing the Timetable Cycle in Nova t6

    I am in a large school with KS 3,4&5. The Cycle and Model and timetables have all been completed for a 6 period day.
    Is there any way I can change the cycle to a 7 period day without losing alll the bands and scheduling ?
    Thanks jdk

  2. #2

    Join Date
    Mar 2007
    Location
    Heywood, Lancs
    Posts
    226
    Thank Post
    7
    Thanked 54 Times in 49 Posts
    Rep Power
    29
    Changing the cycle should not affect the bands at all - bands are independant of where they are scheduled.
    If you are adding a period at the end of a day, it should be possible to do this without breaking the existing schedule. I think the problem would arise if you were trying to insert a period
    in the middle of a day, when you would get problems with broken double periods.

  3. #3

    vikpaw's Avatar
    Join Date
    Sep 2006
    Location
    Saudi Arabia
    Posts
    5,956
    Thank Post
    775
    Thanked 1,487 Times in 1,234 Posts
    Rep Power
    367
    Plus save you file with a different name, and you can see the effects of changes with no ill effect.
    I had a play, and the scheduling did go, but everything else seemed okay.



SHARE:
+ Post New Thread

Similar Threads

  1. [SIMS] Moving lesson times in Nova T6 [Solved]
    By EJT in forum MIS Systems
    Replies: 3
    Last Post: 6th October 2011, 11:04 AM
  2. [SIMS] Periods in Nova-T6
    By strength_10 in forum MIS Systems
    Replies: 5
    Last Post: 9th July 2011, 09:50 AM
  3. [SIMS] Creating Intervention Groups into existing blocks in Nova T6
    By ellisteph10 in forum MIS Systems
    Replies: 4
    Last Post: 30th March 2011, 10:58 AM
  4. Turning off one per day rule in nova t6
    By tony82 in forum MIS Systems
    Replies: 3
    Last Post: 14th June 2008, 12:15 AM
  5. Changeing teachers in nova t4
    By Jamie_a in forum MIS Systems
    Replies: 0
    Last Post: 25th May 2007, 09:31 AM

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •