How do you do....it? Thread, School rewire. IT contingency planning. in Technical; We have a major rewire of the school happening in the Summer. I have not lived through one of these ...
-
26th April 2012, 12:42 PM #1 School rewire. IT contingency planning.
We have a major rewire of the school happening in the Summer. I have not lived through one of these before!! What planning can I put in place to preserve the network and ensure services continue. I'm told that there will be staff needing network access during the period of the work. I suppose the good news is I have been asked at an earlyish stage and can ask for inclusion of such as a filtered supply to the server room.
-
-
IDG Tech News
-
26th April 2012, 12:43 PM #2 Electrical re-wire I take it?
Ben
-
-
26th April 2012, 01:35 PM #3 Best of luck with it, over the course of the building work here (a massive rebuild of over 50% of the school and adding more) it was initially the plan that the network would still need to be accessible. After weeks of meetings, some work beginning and cables starting to come out / power being shut off the SLT realised that it just wasn't feasible to have all-access all the time while the work was going on. We did the best we could but we ended up with areas of the school with no power / no network for weeks at a time, people had to move to another area of the school if they wanted to get online / check email / google etc.
Get printers set up with USB cables if the area they are in will likely not have power to the switch they are connected to, try and make sure that the server room has power at "high capacity" times of the day, but really the best way to avoid problems is to pre-warm people that they might lose access, may have to move to another area in the building for certain tasks, etc.
-
Thanks to Pete10141748 from:
speckytecky (26th April 2012)
-
26th April 2012, 01:41 PM #4 If you mean remote access during the holidays what UPs's do you have? you might be able to get some temp air-con units and extension leads to a UPS if you have a decent one with Commando socket inputs and run it off generators
t
-
-
26th April 2012, 02:14 PM #5 Sorry Ben - yes that's the one.

Originally Posted by
plexer
Electrical re-wire I take it?
Ben
-
-
26th April 2012, 02:16 PM #6 Write it into the contract that on A-Level & GCSE results days (and the day before), power must not be interrupted to anything required to process results.
-
-
26th April 2012, 02:16 PM #7 UPS wont be adequate we are talking of the juice being off for days not hours.

Originally Posted by
glennda
If you mean remote access during the holidays what UPs's do you have? you might be able to get some temp air-con units and extension leads to a UPS if you have a decent one with Commando socket inputs and run it off generators
t
-
-
26th April 2012, 02:34 PM #8 Generators it is then 
Big ones. Diesel.
Ben
-
-
26th April 2012, 02:46 PM #9 One thing we had a problem that two summers ago the school was having it's supply uprated and the generators where not allowed to run 24x7 they were started up at 0800 and turned off at 1630h. Also if it is just internal they should be able to do your feed to the Server room 1st and switch it over quickly. The SMT are mad if they are allowing staff in to the building it is so disruptive with no power they should stop staff coming in.
-
Thanks to nicholab from:
speckytecky (26th April 2012)
-
26th April 2012, 03:03 PM #10 
Originally Posted by
speckytecky
UPS wont be adequate we are talking of the juice being off for days not hours.
Have you considered relocating your servers and some of your workstations to another school over the summer holidays.
-
Thanks to K.C.Leblanc from:
speckytecky (26th April 2012)
-
26th April 2012, 03:33 PM #11 
Originally Posted by
nicholab
One thing we had a problem that two summers ago the school was having it's supply uprated and the generators where not allowed to run 24x7 they were started up at 0800 and turned off at 1630h. Also if it is just internal they should be able to do your feed to the Server room 1st and switch it over quickly. The
SMT are mad if they are allowing staff in to the building it is so disruptive with no power they should stop staff coming in.
Hireable generators should be able to run 24/7 at near silent speeds - they are designed to do so and as long as you get a decent fuel cell it should be fine and no/low fire risk.
-
Thanks to glennda from:
speckytecky (26th April 2012)
-
30th April 2012, 06:06 PM #12 I've been in this boat, and even if you write it into the plans that area A is supposed to be on at time X, and area B at time Y, it isn't going to happen. The work will get started, and you'll quickly learn a new dirty phrase, Change Order. Pack your people up and move them out of harms way. Trust me, it'll save you much grief.
-
Thanks to Duke5A from:
speckytecky (30th April 2012)
-
30th April 2012, 06:23 PM #13 Thanks Duke5A and the rest of you with useful replies. It looks like the best option is establishing the Servers in a remote building on the site which is away from the main building and having a limited service from there. That said the access for the broadband is in the main building so I'm stuffed as far as that goes probably anyhow. What I'm thinking now though is having been asked whilst this is still in the planning stage to get some decent network cabling put in whilst this is all being done - I suspect that in order to comply with various regs the current grey coloured Cat5 will be replaced by them anyhow. We haven't in reality got a decent set up when it comes to network switches several long Cat5 runs that have got to be well over 150M between daisy chained switches so probably need to look at that as well.
-
-
30th April 2012, 09:00 PM #14 
Originally Posted by
pete
Write it into the contract that on A-Level & GCSE results days (and the day before), power must not be interrupted to anything required to process results.
Good practice for this is for no change to be made after 12 noon on the Monday, which allows for Monday afternoon and all day tuesday to try to fix any issues should they arise. The system should need to be working from first thing on Wednesday on both weeks and this will give a buffer in case something goes wrong. If this means that they scrap any work in those two weeks then so be it.
Also remember that a lot of IT access is generally needed now for students looking to go through clearance and downtime due to electrical work can affect this whether it is on the friday after A Level results or if you run your email in-house as it will be needed on almost permanently for the next week and a half.
Also, with a growing number of year 11 students looking at other educational institutes or apprenticeships then they too are likely to need a lot of IT access after their results.
-
-
2nd May 2012, 02:16 PM #15 Generators..... Power extensions...... Wi-fi hotspots + hubs ....... to be honest it sounds like it's one of those ones where you will have to plan for the worst.
-
SHARE: 
Similar Threads
-
By Dos_Box in forum General Chat
Replies: 40
Last Post: 22nd March 2011, 08:36 PM
-
By sidewinder in forum General Chat
Replies: 39
Last Post: 11th September 2009, 08:01 PM
-
By chrisa in forum Educational IT Jobs
Replies: 0
Last Post: 22nd February 2008, 12:54 PM
-
By pinemarten in forum General Chat
Replies: 22
Last Post: 21st February 2007, 01:18 PM
-
By GrumbleDook in forum Educational IT Jobs
Replies: 0
Last Post: 29th October 2006, 03:33 PM
Thread Information
Users Browsing this Thread
There are currently 1 users browsing this thread. (0 members and 1 guests)
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules